Fighting the Epidemic Together, Overcoming Difficult Times—Part Ten: Resuming Work and Production to Ensure Delivery Deadlines—Spendide Employees Are Taking Action


Since resuming work on February 10, the biggest challenge facing Dalian Sinfine’s Production Management Department has been the disruption of production schedules and delivery deadlines. An important export project in the Precision Air Conditioning (hereafter referred to as CR) Division is also grappling with this situation. To meet customer demands, Dalian Sinfine promptly coordinated a response. After extensive communication among marketing, the exporting party, and the customer, the shipment date was ultimately rescheduled for February 20. As this was the first time assembling FU‑type components, the units had to be fully assembled and successfully commissioned before leaving the factory—leaving Sinfine’s team with very little time. For the assembly team, it was their first experience working with laminated stainless steel products; lacking relevant process expertise, they discovered upon removing the laminate and wiping the stainless surface with alcohol that unsightly streaks remained—serious quality issues. After consulting with specialized manufacturers, an emergency cleaning procedure was devised, expanding the original three-step cleaning process to seven steps and doubling the workload. The Production Management Department urgently reassigned three staff members to handle the first five steps of the cleaning process. Workers donned double-layered gloves during cleaning, and these three reinforcements worked continuously for two days, each shift lasting over ten hours. Upon removing their gloves, they found their fingers severely chapped and cracked. In addition to the initial assembly challenges, pandemic‑related protective measures could not be relaxed. Assembly workers donned cleanroom suits and layered masks every day. Using double‑layer high‑protection masks often led to oxygen deprivation, while the goggles attached to the cleanroom suits would fog up under the mask’s influence, causing dizziness and blurred vision. Despite these difficulties, they remained undaunted: when short of breath, they stepped into an empty corner to take a few quick, deep breaths; when their vision blurred, they wiped the goggles clear and pressed on with the task, demonstrating Sinfine’s unwavering resilience and fearless determination. At this point, the complete assembly was still unfinished. To avoid delaying shipment, they had no choice but to assemble and package simultaneously—packing immediately after each unit was assembled, with absolutely no room for delay. Experienced technicians were deployed to the front lines to assist with assembly and resolve on‑site issues; the Quality Assurance Department swiftly reallocated personnel to inspect the products; and the Planning and Dispatch Department coordinated with packaging and shipping partners. With everyone pulling together, by 10 p.m. on the evening of the 19th, all product assembly, commissioning, and packaging tasks were finally completed, enabling smooth shipment on February 20. As of March 20, more than twenty projects have already been shipped. In the face of the pandemic, Sinfine’s team shows no fear; when confronted with critical production responsibilities, they are even less likely to back down. By ensuring both quality and timely delivery, Dalian Sinfine fulfills its commitments in its own unique way. The Dalian Sinfine Production Management Department remains steadfast in delivering on its mission!

Since resuming work on February 10, the biggest challenge facing Dalian Spind’s Production Management Department has been the disruption of production schedules and delivery deadlines. An important export project under the Precision Air Conditioning (hereinafter referred to as CR) Division is also experiencing the same situation. To ensure customer requirements are met, Dalian Spind has promptly coordinated with relevant parties.

After extensive communication among marketing, the exporter, and the customer, the shipment date was ultimately rescheduled to February 20. As this was the first time FU components were being installed, the units had to be fully assembled and thoroughly tested before leaving the factory—leaving little time for the Sibinde team. During the initial assembly of laminated stainless‑steel products, the process engineering team lacked relevant experience; after removing the laminate and wiping the stainless‑steel surface with alcohol, they discovered persistent, irreparable blemishes—clearly a serious quality issue. Following consultations with the supplier, an emergency cleaning procedure was devised, expanding the cleaning process from three steps to seven and doubling the workload. The Production Management Department promptly assigned three dedicated personnel to handle the first five steps of the cleaning sequence. Workers were required to wear double gloves, and these three reinforcements worked continuously for two days, each shift lasting more than ten hours. Upon removing their gloves, they found severe chapping and cracking on their fingers. Meanwhile, the CR assembly team often didn’t get home until nearly midnight, only to rise at dawn the next day to catch the shuttle bus and resume work.

Aside from the initial challenges of assembly, protective measures during the pandemic must remain stringent. Assembly workers don their cleanroom suits each day and don an additional face mask. Using double-layer, high‑protection masks can easily lead to oxygen deprivation, while the goggles attached to the cleanroom suit tend to fog up under the mask’s influence, causing dizziness and blurred vision. Despite these numerous obstacles, they remain unwavering: when oxygen levels drop, they step into a quiet corner to take a few deep breaths of fresh air; when their vision blurs, they wipe the goggles clean and carry on with their work, demonstrating the Spindel team’s resilience and fearless determination.

At this point, the entire machine had still not been fully assembled. To avoid delaying shipment, we had to assemble and package simultaneously—packing each unit immediately upon completion, with no room for even the slightest delay. Experienced technicians were deployed on the front lines to assist with assembly and resolve on-site issues; the Quality Assurance team promptly assigned personnel to inspect the products; and the Planning and Scheduling Department coordinated with the packaging and shipping vendors. With everyone working at full capacity, we successfully completed all assembly, debugging, and packaging tasks by 10 p.m. on the 19th, and shipped the orders smoothly on February 20.

As of March 20, more than 20 project‑related shipments have been completed. In the face of the pandemic, Sifand employees remain undaunted; and when it comes to the critical task of production, they are even less likely to shy away. Ensuring quality and meeting delivery deadlines—Dalian Spindel fulfills its commitments in its own unique way. The Production Management Department at Dalian Spindel is committed to delivering on every promise!